Hamilton Marketplace

This project consisted of complete site and infrastructure development on 277-acres for a shopping center consisting of nearly 1 million-square-feet of retail space. Construction of the project site required compaction of 200,000 cubic yards of soil. Not only was Brinkmann able to fast track the infrastructure project so new retail businesses could open in time for the critical holiday shopping season, but the Brinkmann team provided $2 million in savings to the client - with innovative solutions such as underground piping and modern sewer design.